Frio St. Project Update

Updates for March 2017

 

Special Notice

 

Via Bus Stops At U.T.S.A. are temporarily moved to the first southern pickup.

  • Installing CPS Gas.
  • Pouring Bus Pads in front of UTSA.
  • Constructing sidewalk and curb south of Buena Vista.

**PLEASE NOTE: ALL WORK IS SUBJECT TO FAVORABLE WEATHER CONDITIONS** 

 

 

 

Gas work at Commerce

 

 

Bus Pad at UTSA

 

 

Trench for Gas installation

 

 

THANK YOU FOR YOUR PATIENCE AS WE IMPROVE YOUR COMMUNITY.

 

 

     

If you have questions about the project, please contact:

  

Richard Casiano Capital Projects Officer, TCI, City of San Antonio

210-207-8218, richard.casiano@sanantonio.gov

 

or 

 

http://www.sanantonio.gov/

 

 Transportation & Capital Improvements (TCI)

PO Box 839966
San Antonio, Texas 78283-3966
210-207-8022

  

 

 

 

Stay Connected

Facebook  Twitter    View our videos on YouTube

 

 

Transportation & Capital Improvements (TCI), PO Box 839966, San Antonio, TX 78283-3966

 

 

Sent by tciinfo@sanantonio.gov in collaboration with